Civil Operations
Our multi-skilled civil engineering team has the experience and
track record to ensure your civil construction project is delivered
safely, efficiently and profitably.
Depend on us, for the delivery of a truckload of material, the
successful completion of a multi-million dollar civil construction
project - or anything in between. Our diverse range of services
include:
- site preparation

- bulk earthworks
- major concrete works
- road construction
- road network maintenance
- bridge construction and maintenance
- rail construction
- dams
- pipelines
- supply of quarried material
- regional
accommodation solutions
- general civil services through established regional depots
The major projects BGC Contracting have completed are listed
below (click to expand for more info on each project), to view our
current projects please view our Current Projects:
Term Network Contract 1 - Kimberly Region | Main Roads WA | $160 million
Term10 years
CommencedNovember 2000
Project Details
Maintenance of approximately 2120
km of road network for Main Roads WA in the Kimberley Region. This
includes routine maintenance, periodic maintenance, rehabilitation
works, asset management of off-road assets, data management and
minor improvement works.

expand/collapse
Term Network Contract 2 - Pilbara and Gascoyne Region | Main Roads WA | $250 million
Term10 Years
CommencedNovember 2000
Project Details
Maintenance of approximately 4,280
km of road network for Main Roads WA in the Pilbara and Gascoyne
Regions, and the Great Northern Highway north of Mount Magnet in
the Mid West Region. This includes routine maintenance, periodic
maintenance, rehabilitation works, asset management of off-road
assets, data management and minor improvement works.
expand/collapse
Sino Iron Project - Crusher Slots | CITIC Pacific Mining | $30 million
Term8 months
CommencedJanuary 2011
Project Details
The contract required BGC to build
two 21m high reinforced earth walls to house Primary Crushers #3
and #4 as part of the mine processing area. The scope of work
involved extensive explosive excavation and processing of the
excavated material to produce select fill for the reinforced earth
retaining walls.

expand/collapse
Sino Iron Project - Pipe Rack Footings | MCC Mining (WA) | $20 million
Term6 months
CommencedNovember 2010
Project Details
The scope for this project was
to construct the pipe rack footings and pedestals, which when
completed linked the Power station to both the AG Mills and Ball
Mills. The total number of footings was 484 with another 95 precast
off site.
expand/collapse
Cape Preston Desalination Plant - Civil Works | CITIC Pacific Mining | $40 million
Term6 months
CommencedNovember, 2009
Project Details
The scope of work was to
provide services to construct the; Civil, Foundation works; install
Pre-cast concrete elements; install underground GRP piping’s and
manholes, and provide additional concrete foundations necessary to
ready the site for receipt of the modules.
This project was successfully
concluded on the 16th July 2010, well within project budget, on
time and to the client’s full satisfaction
expand/collapse
Sino Iron Project - AG Mill | MCC Mining (WA) | $100 million
Term14 Months
CommencedNovember, 2009
Project Details
The AG Mill contract for MCC Mining
(WA) included some 30,000 cubic metres of concrete in concrete
foundations and extensive piling works. The contract was valued in
the order of $100M.

expand/collapse
Sino Iron Project - Overland Conveyors Works | MCC Mining (WA) | $25 million
Term5 months
CommencedJuly 2010
Project Details
The
scope of works comprises the supply of all supervision, labour,
materials, plant and equipment necessary to construct Overland
Conveyers Foundations (concrete structures) in the Area 10 Crushing
Plant of Citic Pacific’s Sino Iron mining project. The Overland
Conveyers form the link between the Coarse Ore Crushing Slots and
the Coarse Ore Transfer Station & Ore Bin
expand/collapse
Sino Iron Project - Stockpile Underground Tunnel Works | MCC Mining (WA) | $75 million
Term17 months
CommencedApril 2010
Project Details
This
Scope of Work includes the supply of all supervision, labour,
materials, plant and equipment, tools, consumables and all other
items necessary for the installation of concrete works for the
stockyard underground tunnel, for the Sino Iron
Project.
The
underground tunnel is part of the coarse ore stockpile which is the
link between transfer stations and the pebble crushers. The coarse
ore stockpile consists of the underground tunnel and six reclaim
tunnels that branch off towards the pebble
crushers.

expand/collapse
ECI - Kimberley (Great Northern Highway)| Main Roads WA| $105 million
Term29 Months
CommencedSeptember 2007
Project Details
BGC Contracting lead a Joint
Venture team (named Team Savannah) which included Laing O'Rourke
and Maunsell, to design and construct three new bridges and make
improvements to two major sections of the Great Northern Highway in
the Kimberley region of Western Australia. The project was
delivered under an Early Contractor Involvement (ECI) contract.
This is a relationship based form of contract that has not been
used previously by Main Roads WA.
(Est JV Value: $105.0 million)

expand/collapse
Pluto LNG - Site B O&U Civil Works | Woodside Energy | $230 million
Term13 Months
CommencedNovember 2008
Project Details
The project comprised of the
civil construction works associated with the Offplot and Utilities
section of the gas processing plant.
The scope of
work included reinforced concrete foundations (20,000 m3),
reinforced concrete pavements (17,000m2), detailed earthworks
comprising some 250,000 m3 of engineered backfill, underground
electrical cable installation (400 km), pre-cast and insitu
trenching, firewater GRE pipework (4km), electrical,
instrumentation and communication works, underground services,
stormwater surface drainage, roads and fences

expand/collapse
Pluto LNG - Concrete LNG Tanks | CB&I (Subcontract to Woodside Energy) | $65 million
Term12 Months
CommencedDecember 2008
Project Details
BGC Contracting subcontracted to
CB&I on this package.
CB&I's initial scope of work
includes the engineering, procurement, construction and
pre-commissioning of two 120,000 cubic meter full containment LNG
storage tanks, three condensate tanks and associated civil, piping,
electrical and instrumentation work.
BGC’s scope on the Pluto LNG Tank
Project involved site works, concrete shell & roof construction
for 5 storage tanks. 2 Number LNG storage tanks and 3 Number
condensate storage tanks.
LNG Storage
Tanks
2 x 72m diameter / 47m high
Reinforced Concrete LNG Storage Tanks, including construction of
all concrete to bases, walls and roofs. (23,000m3 of concrete)
Condensate
Tanks
Earthwork foundations for 2 x 66m
diameter tanks, and 1 x 27.5m diameter tank. (16,000m3 of
earthworks)

expand/collapse
Kestrel - Mine Extension Civil Works| Rio Tinto Coal Australia| $50 million
Term18 Months
CommencedSeptember 2008
Project Details
The work under this Contract
consists of all earthworks and civil works for the excavation of
two (2) box-cuts, the installation of a pre-cast portal arch system
in each box-cut and the subsequent backfill of each box-cut. The
scope also includes the construction of holding and sedimentation
dams, with the excavated material being utilised to create the ROM
stockpile areas, the Mine Infrastructure Area (MIA), diversion
bunds, environmental bunds and various lay-down areas. A 5,200m
mine access road is also included in the scope of work.
(Est Value: $50.0 million)

expand/collapse
Clermont - Overland Conveyor Civil Works | Rio Tinto Coal | $15 million
Term12 Months
CommencedNovember 2008
Project Details
The works under this project consists of all
earthworks and civil works necessary to establish the formation for
the installation of the Overland Conveyor between Clermont Coal
Mine and Blair Athol Coal Mine.
The scope included Unsealed
pavement construction, stormwater culverts, floodway crossings,
road crossing, machinery crossing, Queensland Rail Underpass, Blair
Athol Mine Coal Haul Road Underpass, 4.0m and 4.5m spun steel
culverts and sedimentation dams
expand/collapse
Clermont - Onsite Civil Works | Rio Tinto Coal | $20 million
Term13 months
CommencedOctober 2008
Project Details
The construction components in
this project included clearing and grubbing, topsoil removal and
re-use, construction of light vehicle roads including bitumen
seals, industrial stockpile areas including foundations
and drainage structures and sedimentation basins.
Also included within the scope was
the construction 95,000m3 of pavement of the Northern
Haul Road (3.6km), construction of 450,000m3 of rock
earthworks for the In Pit Crushing Conveyor in conjunction with Rio
Tinto Coal’s mining fleet, reinforced earth wall for the ROM and
engineered backfill behind the structure and paving and trimming
the ROM
expand/collapse
TPI - Rail Earthworks and Culverts | Fortescue Metals Group | $160 million
Term16 months
CommencedNovember 2006
Project Details
The Project comprises three contractors completing the
embankment construction for the 260km railway line between Port
Hedland and Cloud Break Mine, including the associated drilling,
blasting and culvert requirements along this length. The Project
included working adjacent to and the crossing of operational
infrastructure including the Great North Highway, the existing
BHPBIO Mt Newman railway line and others of a more minor
nature.
The total works include a quantity of 3.5million m3
of rock to be drilled and blasted on the Project, forming part of
the total of 7million m3 of fill that is required. As
the Project is spread over 260km, and with a tight completion
schedule the planning and logistics form a vital part in the
completion of the Project.

expand/collapse
Pluto LNG - Site A Site Preparation | Woodside Energy | $100 million
Term23 months
CommencedDecember 2006
Project Details
Re-location of 44 Heritage Artefacts (rock art) to an on-site
Preservation Area. Drilling, blasting and excavation of
638,000m3 of rock. Placement &
compaction of 100,000m3 of rock fill.
Haulage and processing of
65,000m3 of rock into road base
material. The remaining 473,000m3 of
rock fill was stockpiled for future use. Establishment of a
site office complex for the client. Workforce peaked at 110.
including specialist subcontractors.
expand/collapse
Train V LNG - Brownfields | Woodside Energy | $85 million
Term12 months
CommencedMay 2006
Project Details
The Brownfield package was for Woodside Energy Limited's
Train V LNG Expansion Project. The works were located within
the existing North West Shelf Venture's Onshore Gas Plant located
on the Burrup Peninsula. Train V is immediately adjacent Train IV
and is practically a "copy".
The scope of works includes concrete foundations (10,100m3),
earthworks, underground cable installation, pre-cast and insitu
trenching, pipework, electrical, instrumentation and communication
works, underground services, stormwater drainage, smoke detection
systems, HVAC, building works including structural steel, cladding
and architectural finishes. The scope also includes for
relocation of existing facilities and services.

expand/collapse
Train V LNG - Greenfields | Woodside Energy | $80 million
Term18 months
CommencedNovember 2005
Project Details
The Greenfield package was for Woodside Energy Limited's
Train V LNG Expansion Project. The works were located within
the existing North West Shelf Venture's Onshore Gas Plant located
on the Burrup Peninsula. Train V is immediately adjacent Train IV
and is practically a "copy".
The scope of work for the Greenfield package involved the
installation of approximately 22,000 cubic metres of structural
concrete and footings, the installation of approximately 400
kilometres of electrical and instrumentation wiring, building works
(including HVAC and smoke detection system) and as well as
associated civil works for the complete LNG V processing train.

expand/collapse
Burrup Fertlisers - Sitewide Concrete | Burrup Fertilisers | $40 million
Term14 months
CommencedDecember 2003
Project Details
Burrup Fertilisers Pty Ltd is building and will operate a 2,200
MTPD liquid Ammonia Plant at the King Bay - Hearson Cove industrial
area on the Burrup Peninsula. The Plant will produce and export
Ammonia for the world market.
The package involved the placement of approximately
19,000m3 of concrete, 1,500 tonne of reinforcement with associated
earthworks and drainage.
BGC supplied concrete from our own batch plant.

expand/collapse
Train IV LNG - Site Preparation | Woodside Energy | $30 million
Term9 months
CommencedFebruary 2001
Project Details
The Project was for the $1.5 Billion LNG Train 4 Expansion for
Woodside Energy Limited at the Burrup Peninsula in Karratha Western
Australia.
The Train 4 Site Preperation Package was for
the construction and testing of consolidated rock plate
foundations to support the new LNG Train 4, associated pipe
racks/tracks, substation 2, FAR 16, Sulfinol facility and power
generation facilities. Work included; bulk excavation to remove
unsuitable sub grade material, Crushing of materials to produce
backfill material, Backfilling of site to produce to specified
requirements. Earthworks, concrete work, electrical works and
buildings for the Train 4 facilities. A design and construct
project consisting of 1.3 million tonne of earthworks (including
crushing of rock).
Material sorted utilizing various plant and transported to
crusher. Crushing and screening using a double toggle jaw crusher.
Material hauled from crushed stockpile to excavation area using 85T
dump trucks. Excavation of site area undertaken with 100T excavator
loading into 85T dump trucks. This material was then taken to the
crusher for crushing and screening to provide suitable backfill
material.

expand/collapse
Burrup Fertilisers - Site Preparation | Burrup Fertilisers | $30 million
Term7 months
CommencedApril 2003
Project Details
Burrup Fertilisers Pty Ltd is building and will operate a 2200
MTPD liquid Ammonia Plant at the King Bay - Hearson Cove industrial
area on the Burrup Peninsula. The Plant will produce and
export Ammonia for the world market. The work scope included
the excavation, construction and backfill of concrete ringbeam
foundations for two ammonia storage tanks.
THe package included up to 190,000m3 of rockfill and 50,000m3 of
subbase was imported to site to build the 23 Hectare Pad Area to
receive the world class Ammonia Plant. A further 50,000m3 of
rock was blasted on site to provide the remaining fill required to
complete the pad.
BGC was responsible for installing all electrical, water,
drainage, sewage and communication services. BGC used direct labour
and plant to complete 3,000 metres of stormwater drainage on the
site. Specialist subcontractors were engaged to complete the
other services.
expand/collapse
Train IV LNG - TOT Site Preparation | Woodside Energy | $25 million
Term11 months
CommencedMay 2002
Project Details
The Project was for the $1.5 Billion LNG Train 4 Expansion for
Woodside Energy Limited at the Burrup Peninsula in Karratha Western
Australia.
The initial $12 million contract for ‘Trunkline Onshore Terminal
(TOT) Site Preparation Works' was signed on 31 May 2002 with an
original end date of 31 December 2002. The contract was extended to
include a $9 million concrete works variation. Various additional
works were added progressively to increase the final value to
approximately $23 million.
The Site Preparation Works required 90,000T of rock to be
crushed and placed as foundation material. 180 linear metres of
reinforced concrete walls to be built, with heights varying from 1m
to 5m. Earthworks to be filled with 25,000m3 of cut. Temporary
buildings were supplied and erected for future use by subsequent
erection contractors. Extensive relocation of services needed
within the operational gas plant. The variation works included over
4,000m3 concrete, construction of pipe rack footings, pedestals,
manholes and associated service works.
expand/collapse
TPI - Railway Ballast Supply | Fortescue Metals Group | $25 million
Term12 months
CommencedMay 2006
Project Details
Team 45 is the integrated project management team of Fortescue
Metals Group, The Pilbara Infrastructure, FMG Chichester and Worley
Parsons. Team 45 and Worley Parsons act on behalf of and as
disclosed agent of the Pilbara Infrastructure and FMG
Chichester. The project involves the supply of railway
ballast for the construction of a 260km rail line being built by
FMG. The rail line runs from Port Hedland south to Cloud
Break Mine.
The project involves the quarrying, crushing and delivery of
approximately 720,000 tonnes of minus 53mm ballast.

expand/collapse
Sonoma Coal - (D&C) Mine Infrastructure | Q Coal | $20 million
Term12 months
CommencedDesign: September 2005 - Construction: October 2006
Project Details
Project Managers for the design and construction of on-site
infrastructure requirements for a new coal mine. The scope of
works included in the project were:
-
Assisting developing the master plan for the site and managing
the design of the on-site infrastructure works;
-
3.6 km rail loop including all earthworks / culverts;
-
2 km raw water supply pipeline;
-
Hardstand and offices for mine infrastructure area
(MIA);
-
Access roads to the MIA and coal processing plant and main
road intersection upgrade; and
- Raw water storage dam and Co-disposal dam.

expand/collapse
Train V LNG - MOF Road Upgrade | Woodside Energy | $20 million
Term5 months
CommencedMarch 2006
Project Details
The Material Offloading Facility (MOF) Road Upgrade
package was for Woodside Energy Limited's Train V LNG
Expansion Project. The works were located within the existing
North West Shelf Venture's Onshore Gas Plant located on the Burrup
Peninsula. Train V is immediately adjacent Train IV and is
practically a "copy".
Whilst called the MOF road package, the works are located on the
existing MOF Road on the Burrup Peninsular, this road is used to
transport material from the MOF Wharf to the Train 5 project
site
The scope of work involves the widening of the existing MOF Road
to transport heavy modules from the MOF Wharf to the LNG Train 5
site, works included Drill and Blast, cut to fill, trenching
(electrical and power) installation of electrical and power,
heritage clearing, road seal and traffic control.

expand/collapse
Millennium Coal - Roads, Rail Loop and Dam | Millennium Coal | $20 million
Term6 months
CommencedJanuary 2005
Project Details
The scope of works undertaken during initial construction phase
included:
-
Mine access road and internal road to office / industrial
area
-
Construction of 5.5kms rail loop
-
Installation and placement of 2 x barrel 8 metre diameter
multi plate culverts at Chum Creek
- West and East Environmental Dam and Clean Water Dam.

expand/collapse
Train IV LNG - TSEP Rock Supply | Woodside Energy | $15 million
Term14 months
CommencedJuly 2003
Project Details
The Truckline System Expansion Project (TSEP) was for
the $1.5 Billion LNG Train 4 Expansion for Woodside Energy Limited
at the Burrup Peninsula in Karratha Western Australia.
Supply of rock to protect and stabilise sections of the North
West Shelf Venture's second trunkline. The 130 km trunkline will
link the Venture's offshore gas production and onshore gas
processing facilities. The contract involves the quarrying,
processing, delivery and stockpiling of over 1,000,000 cubic metres
of rock armour. The rock is quarried from a lease held by the
Dampier Port Authority.
A new quarry facility was established at the Dampier Port
Authority which is operated by BGC. The establishment of the quarry
required approval from the EPA and Aboriginal heritage clearance.
An existing diesel fuel line needed to be relocated. The Telstra
Fibre Optic Lines servicing Woodside and Dampier Port Authority
facilities at Dampier also needed to be relocated.
Reclamation works for the construction of a new land backed
wharf load-out facility were undertaken.

expand/collapse
Kemerton - Main Civil Works | Siemens | $15 million
Term12 months
CommencedSeptember 2004
Project Details
The Kemerton Power Station Project is located approximately 150
kilometres south of Perth in the state of Western Australia.
Siemens have been contracted by Transfield Services to construct a
"Peak Load" power station consisting of two turbines with a total
capacity of 260 MW fired by natural gas or low sulphur diesel
fuel. Siemens have engaged BGC Contracting to carry out the
Main Civil Works Contract. This encompasses earthworks, roadworks,
underground piping, concrete works, electrical earthing/lightning
protection, steel erection, cladding and building works. The
project included:
-
4,500 cu. m of excavation;
-
4,200 cu. m of backfill;
-
5,500 cu. m of concrete; and
-
4,000 sq m of roadworks.
The Kemerton Power Station project also involved the erection of
360T of client supplied structural steel primarily to the turbine
buildings. These steel framed buildings were clad (double skin)
with 3000 sq m of cladding.
In addition, BGC constructed the Control Room building. This was
a concrete - framed blockwork building with all the various
building trade activities, together with a suspended concrete slab
roof structure covered with membrane.

expand/collapse
Karratha Gas Plant (KGP) - Security Upgrade | Woodside Energy | $15 million
Term12 months
CommencedJanuary 2007
Project Details
The project comprised the following works which were carried out
at the North West Shelf Venture's Onshore Gas Plant located on the
Burrup Peninsula:- the supply and installation of Security fencing
and gates around the perimeter of the plant, the upgrade of the
Main Gate car park and entry to the Gas Plant, the repair of a
section of damaged seawall on the Eastern side of the plant and the
reinstatement and upgrade of a disturbed roadway at No Name Creek
which is at the Western end of the plant
The scope of works, with a contract sum of approximately AUD
$11.0 million involved the following:-
Security Fence Upgrade - This included the
demolition and disposal offsite of the existing perimeter security
fence and the installation of approximately 6.5 kilometers of new
perimeter security fencing and the installation of approximately 12
new gates at various locations around the plant. A specialist
contractor was engaged to carry out the fencing component of
works.
Car Park Upgrade and security camera service
trenches - The front gate and car park area upgrade
included the removal of old pavement and installation of new
pavement including road base, asphalt and kerbing. This also
included the installation of various components of precast concrete
and also bases for the new lighting as well as miscellaneous
associated civil works required for the main gate security
upgrade.
Repair of Seawall at Eastern end and upgrade of road at
No Name Creek - A section of Seawall (approx 150m long by
batter dimension = 25m) that was washed out during 2005 - 2006
cyclone season required repair prior to the new security fence
being installed. This required the installation of a 20m long 3m
high precast concrete retaining wall and the importation and
placement of approximately 10,000 tonnes of rock armour. A section
or road way was required to be upgraded prior to the installation
of the upgraded security fence at No Name Creek. This consisted of
approx 2,000m2 of roadway box out and removal offsite, installation
of road base and 2 coat chip seal, installation of RCP drainage and
end treatments, and the construction of rock lined V drains on the
sides of each roadway.

expand/collapse
Hail Creek Coal - Clearing and Topsoil Stripping | Rio Tinto Coal | $10 million
Term14 months
CommencedNovember 2003
Project Details
Located 100 kilometres west of Mackay and 35 kilometres
north-east of Nebo, the Hail Creek operation produces coal from one
of the world's largest coking coal deposits. The mine was
officially opened in November 2003. BGC undertook the clearing and
topsoil stripping of this newly established mine site in a Eucalypt
forest area. Works included:

expand/collapse
Middlemount Coal - Haul Road Construction | Anglo Coal | $10 million
Term2 months
CommencedFebruary 2004
Project Details
Construction of 12klm haul road for 160 tonne coal haulers from
mine to coal preparation plant. Strip and stockpile topsoil and
generally prepare the area under the road. Carry out general
earthworks and install reinforced concrete pipe culverts under
road.
Drill, blast and crush hard rock from quarry and place and
compact road base material (sub-base 175mm sub- base, 175mm to
280mm at crown base course). Other associated earthworks, erosion
control and wet land embankment.

expand/collapse
Burrup Fertilisers - Underground Piping | Burrup Fertilisers | $10 million
Term9 months
CommencedJanuary 2004
Project Details
Burrup Fertilisers Pty Ltd is building and will operate a 2,200
MTPD liquid Ammonia Plant at the King Bay - Hearson Cove industrial
area on the Burrup Peninsula. The Plant will produce and
export Ammonia for the world market. This contract involves
the procurement, installation and testing of in ground piping for
the seawater cooling and fire protection piping systems across the
entire site.
The scope included the installation of large diameter glass
fibre reinforced piping. Diameters ranged from 12 inch to 68
inch. Works included excavation, installation and hydro
testing of all piping. Approximately 4000 linear metres of
various size pipes installed. All piping was manufactured
overseas and shipped to Fremantle. Off site works included
prefabrication of pipe spools to reduce the about of on site
labour.
Detailed planning required to:
-
Finalised detail design
-
Procure and import material
-
Prefabrication of pipe spools
-
Installation amongst other mechanical installation
contractors

expand/collapse
Hail Creek - Civils | Rio Tinto Coal | $10 million
Pluto LNG - Shore Crossing | Woodside Burrup (Subcontract with Van Oord) | $10 million
Term4 months
CommencedFebruary 2008
Project Details
The Pluto LNG Project, a liquefaction facility with forecasted
production of 4.3 million tonnes per annum, is located on the
Burrup Peninsula in Western Australia, approximately 20 kilometres
(12 miles) northwest of Karratha. The project is expected to be
completed in 2010.
BGC Contracting was subcontracted to Van Oord for the Shore
Crossing Civil Works Package. The project comprises civil
construction works for Van Oord, to create the transition between
off shore works and on shore works such that the Pluto gas pipeline
can be brought on shore. The scope of works involved the creation
of various on shore lay down areas, creation of a temporary groyne
to be used as an off shore working platform to undertake drill and
blast activities, removal of the groyne and blasted material to
create an off shore to on shore pipeline route. This involved
shifting approximately 8,000 cubic metres of structural material
off shore and stabilising batters to suit the Pilbra marine
environment. On shore drill and blast was also undertaken to
create a clear trench for the on shore portion of the gas
pipeline.

expand/collapse
Ravensthorpe Nickel - Site Establishment | Ravensthorpe Nickel Ops | $5 million
Term6 months
CommencedMay 2004
Project Details
Construction of access roads and preliminary earthworks for the
Ravensthorpe Nickel mine at Ravensthorpe 575km Southwest of
Perth. The package was to devleop the Greenfields site, works
included:
-
Roadworks and drainage;
-
Haul roads;
-
Establishment of barrow areas;
-
Construction of borefields;
-
Plant laydown erea; and
-
Camp site infrastructure.
expand/collapse
Moura - Rehabilitation (2005) | Anglo Coal | $3 million
Term6 months
CommencedMarch 2005
Project Details
Moura Mine is a coking & thermal coal mine and is located
approximately 220kms west of Gladstone. BGC was awarded this second
contract (2005) and is carrying out further dragline spoil regrade
to fit Anglo Coals design criteria.
The work was executed on this project using the following
equipment;
-
1 x 475-3 Komatsu Dozer - fitted with dozer guidance GPS
-
1 x 575-2 Komatsu Super Dozer
-
1 x D11R Caterpillar Dozer
This being the second rehabilitation project (2005) was carried
out ahead of schedule and as a variation to 2004 project, BGC were
asked to bulk push approximately 1 million m3 to uncover
the coal.

expand/collapse
Train IV LNG - Propane Tank Foundation | Woodside Energy | $3.0 million
Term5 months
CommencedNovember 2005
Project Details
The Project was for
the $1.5 Billion LNG Train 4 Expansion for Woodside Energy Limited
at the Burrup Peninsula in Karratha Western Australia.
The package was for the provision of a Consolidated Rock Plate
Foundation for a 200,000m2 Propane storage tank, Liquids Expansion
Project. Project involved removal of loose rock outcrop, drill and
blast and excavate to sound load bearing foundations, screen shot
rock material into required sizes and replace excavation with
rockfill layers to underside of tank foundation level.
Strict controls required, especially during drill and blast
operations considering proximity of LNG gas storage tanks (50
metres) and an operational gas processing plant.
Construct only contract, design supplied by Woodside Energy
Limited.
expand/collapse
Derby Highway - Roadworks and Drainage | Main Roads WA | $3 million
Term3 months
CommencedSeptember 2003
Project Details
Road works on the Derby Highway began adjacent to the Derby
Airport in the Kimberley Region of Western Australia and extended
south for 6.23kms. The project involved the reconstruction of
the existing road to a seal width of 8 metres, and the construction
of flood ways and off-road drainage.
A two-way sidetrack was constructed for use by all vehicles with
a 60km/h speed limit, for the duration of the road works.
Ripping up the bitumen seal on the existing road.
24,000m3 of bulk earthworks (18,000m3 as
spoil and 8,000m3 as fill within the works).
Insitu concrete works for culverts. Preparation of
subgrade. Load, haul and placement of gravel subbase and
basecourse supplied by the Client from a quarry 30kms from the
worksite. Subbase and basecourse stabilisation. Two
coat sealing to floodways and sand sealing elsewhere on the
complete pavement. Construction of surface drains.
Traffic sign and guide post installation. Linemarking.

expand/collapse
Bulk Liquids Expansion - Propane Tank Foundation | Woodside Energy | $3 million
Term5 months
CommencedNovember 2005
Project Details
Provision of a Consolidated Rock Plate Foundation for a
200,000m2 Propane storage tank, Liquids Expansion Project, North
West Shelf, Burrup Peninsula. Project involved removal of
loose rock outcrop, drill and blast and excavate to sound load
bearing foundations, screen shot rock material into required sizes
and replace excavation with rockfill layers to underside of tank
foundation level.
Strict controls required, especially during drill and blast
operations considering proximity of LNG gas storage tanks (50
metres) and an operational gas processing plant.
Construct only contract, design was supplied by Woodside Energy
Ltd.
The Burrup Peninsula is an area of special environmental
significance and as such strict controls were required during the
project.
expand/collapse
Gregory - Rehabilitation | BHP Billiton Mitsubishi Alliance (BMA) | $3 million
Term2 months
CommencedJune 2006
Project Details
This project involves pushing approximately 2 million bank cubic
metres of dragline spoil and placing of topsoil to facilitate BMA's
rehabilitation at Gregory Mine .
The works reuqired BGC Contracting to push material utilising 5
dozers, 4 x D11R's, 1 x Komatsu 575 Super Dozer, The D11R Dozers
are equipped with a GPS Dozer Guidance System. For the topsoil
placement we utilised 657 Scrapers.

expand/collapse
Blackwater - Concrete Works | BHP Billiton Mitsubishi Alliance (BMA) | $2 million
Term2 months
CommencedNovember 2006
Project Details
The project comprises the construction of two x 865m concrete
roads / drains for the new CHPP load out area. The scope of works
includes excavation to level and placement of approximately
2,000m3 reinforced concrete.

expand/collapse
Moura - Rehabilitation (2004) | Anglo Coal | $2 million
Term4 months
CommencedOctober 2004
Project Details
Moura Mine is a coking & thermal coal mine and is located
approximately 220kms west of Gladstone. BGC carried out dragline
spoil regrading, ripping and aerial seeding of approximately 1.2
million m3. This was the first contract of 2, Moura Rehabilitation
2005 followed.
The work was executed on this project using the following
equipment;
-
§ 1 x 475-3 Komatsu Dozer - fitted with dozer guidance
GPS
-
§ 1 x 575-2 Komatsu Super Dozer
-
§ 1 x D11R Caterpillar Dozer
-
§ 1 x D8N Caterpillar Seeding Tractor
The successful early completion of this project led to the
awarding of a second rehabilitation project (2005).

expand/collapse
Cement Australia - Rail Siding | Frost Enterprises Pty Ltd | $1 million
Term2 months
CommencedMarch 2004
Project Details
Sole contractors for the construction of the Cement Australia
Rail Siding and Loading Pad facility at Frost Enterprises Taragoola
limestone mine. Project included cut to fill earthworks,
installation of RCP pipes and drainage structures. The loading pad
had 600mm, 2.5 road base laid and compacted to 95%.

expand/collapse